TKO Campus: Latest Updates 18.01.2018

This article will be updated regularly to keep you posted on the development of the campus before it opens in September 2018! One year to go!

 

TKO - Progress

18.01.2018

New Campus is taking shape!

08.12.2017

FIS presents enormous artwork for Hong Kong to enjoy

26.09.2017: Secondary School Building structure completed

It's amazing how quickly both the Primary and Secondary School buildings have gone up - both have now been completed!

22 out of 132 GRC panels have been installed to date and the Primary School lift shaft  has been handed over to Schindler.

30.08.2017: Primary School Building structure completed

We are excited to see how quickly our new campus at Tseung Kwan O is progressing! 

Over the summer, the Primary School Building structure was completed. The 4/F of Secondary School has also been completed - one more floor to go!

The end of August will see the Primary School GRC Panel Installation begin and delivery of the precast gymnasium façade is expected from the end of September.

Watch this space for regular updates and photos!